Installation
2×660 MW
Coal-fired plant, northern China
Mill Type
Vertical Roller
Medium-speed, hydraulic loading
Mills Served
12 Mills
6 per boiler · 2 circuits
Design Feed Rate
248.3 t/h
Combined, both boilers
In Service Since
2015
10+ years · no system downtime

Automatic Mill Reject Handling at 2×660MW Plant

12 Coal Mills, One Automated System, Running Since 2015

This case study documents the retrofit of a coal-fired power plant's mill reject discharge system, replacing manual forklift transfer with a negative-pressure vacuum conveying system across twelve coal mills.

THE PROBLEM

What Was There Before

Each mill discharged rejects into a 0.8 m³ pyrite hopper mounted on the mill floor beneath the mill body. From there, a hydraulic forklift transferred accumulated material to a designated storage area.

When discharge volumes ran high, the forklifts couldn't keep pace and hoppers backed up into the mill discharge path.

Gate valve and cylinder seal attrition

Pneumatic gate valves at mill discharge ran continuously in a hot, abrasive environment. Cylinder seals failed on a recurring basis; external valve body leakage was a standing maintenance item across all twelve mills. Parts consumption ran approximately ¥120,000 (~$18,500)/year installation-wide.

200°C material at an open transfer point

Mill rejects exited at up to 200°C. Material in the hopper reached up to 200°C and released SO₂ and CO gases — a documented occupational hazard for workers.

Fugitive dust on every transfer cycle

Every forklift cycle stirred the material and generated airborne coal dust. The boiler basement was a chronically dirty environment with no practical path to improvement under the existing system.

Three dedicated FTEs with no path to reduction

Two forklift operators — one per boiler — and one housekeeping worker. Total annual cost: ¥550,000 (~$84,500) in wages and benefits. Two forklifts added another ¥100,000 (~$15,500) in depreciation and maintenance. At US labor rates, the equivalent headcount costs substantially more.

A worker manually shovels mill rejects. Hopper temperatures at this location run up to 200°C during normal operation.


THE SOLUTION

What Was Installed

The system uses a positive-displacement Roots blower to draw the entire conveying network to a sustained vacuum of up to −75 kPa. From each mill's pyrite hopper, sealed conveying pipelines route overhead through the boiler basement to a central cyclone/bag-filter separator. Separated rejects drop by gravity into a storage silo; filtered air passes through an air-cooled heat exchanger and discharges to atmosphere via the bag collector.

The twelve mills run as two independent six-mill circuits — one per boiler — each with its own blower rated at 4,500 m³/h. Conveying capacity reaches 30 t/h, handling material up to 50 mm particle size. That covers the full reject stream including occasional oversized tramp material that gets through the mill internals.

No personnel. No forklifts. No open transfer points. The system cycles through all hoppers automatically under DCS control, 24 hours a day.

−75 kPa
Maximum system vacuum
30 t/h
Conveying capacity
50 mm
Maximum particle size
4,500 m³/h
Rated blower airflow
260 °C
Filter bag temperature rating
≤85 dB(A)
Power unit noise at 1 m

OPERATING RESULTS

BY THE NUMBERS

The system has run continuously since 2015 commissioning. Maintenance has consisted of scheduled elbow liner inspection and periodic replacement — consistent with running abrasive, angular reject material at up to 30 t/h through steel elbows. In over ten years of operation, maintenance has been limited to scheduled elbow replacement — no operational interruptions have been attributed to the conveying system.

The cost data comes from the plant's pre-retrofit accounting and post-installation operating records.

Cost Item Before Retrofit After Retrofit
Gate valve and seal replacement, 12 mills ¥120,000 (~$18,500)/yr Eliminated
Forklift depreciation and maintenance, 2 units ¥100,000 (~$15,500)/yr Eliminated
Forklift operators, 2 FTE (wages + benefits) ¥400,000 (~$61,500)/yr Eliminated
Housekeeping, 1 FTE (wages + benefits) ¥150,000(~$23,000)/yr Eliminated
System electricity and maintenance ¥170,000 (~$26,000)/yr
Total Annual Cost ¥770,000(~$118,500)/yr ¥170,000(~$26,000)/yr

Operating cost methodology: ¥170,000/yr calculated from actual runtime data — one 660 MW boiler running 5,000 hr/yr at ¥0.30/kWh, one conveying cycle per hour. Cross-checked and confirmed against a separate 1,000 MW unit installation.   Note for US plants: Labor figures reflect Chinese wage rates.

3
FTE removed from
mill reject duty
¥170K
Total annual operating cost
across 12 mills (~$23,400 USD)
10+
Years continuous operation
zero system-caused downtime

GET IN TOUCH

Talk to us about your mill reject system.